A Level Accounting (9706)•9706/13/O/N/23

Explanation
Under-Absorbed Overheads Formula
Steps:
- Calculate absorbed overheads: 122,000.
- Under-absorbed overheads = actual overheads - absorbed overheads.
- Given under-absorption of 122,000 + 125,000.
Why D is correct:
- Under-absorbed overheads are defined as actual overheads exceeding absorbed overheads (rate × actual hours), so actual = absorbed + under-absorbed.
Why the others are wrong:
- A: Equals budgeted absorbed overheads (120,000), ignoring actual hours and under-absorption.
- B: Overstates by adding under-absorption to budgeted absorbed (3000 = $123,000, but uses wrong base).
- C: Subtracts under-absorption from absorbed (3000 = $119,000), implying over-absorption.
Final answer: D
Topic: Traditional costing methods