Missing hourly wage rate prevents calculation Steps:
- Identify regular pay: Each of 8 employees works 40 hours at an unspecified rate of $ per hour, so per-employee regular pay is 40 × (missing rate).
- Check bonus eligibility: Team produced 560 units, below 600-unit threshold, so no bonus ($40 per excess unit, shared equally).
- Calculate total pay per employee: Only regular pay applies, but rate is unknown.
- Conclude: Cannot compute numerical pay without the hourly rate.
Why A is correct:
- Not applicable; insufficient data to verify any option.
Why the others are wrong:
- B: Assumes incorrect bonus inclusion or rate.
- C: Likely overestimates with full bonus on all units.
- D: Underestimates, perhaps ignoring hours worked.
Not enough information. Final answer: Not enough information.