A Level Accounting (9706)•9706/13/O/N/21

Explanation
Fixed Overhead Absorption Variance
Steps:
- Calculate predetermined absorption rate: budgeted fixed overheads ÷ budgeted hours = 150,000 ÷ 10,000 = 15 per hour.
- Calculate absorbed overheads: absorption rate × actual hours = 15 × 11,000 = 165,000.
- Subtract absorbed from actual overheads: 170,000 - 165,000 = 5,000.
- Positive difference means under absorption by 5,000.
Why B is correct:
- Under absorption equals actual overheads minus absorbed overheads (using predetermined rate based on budgeted data), resulting in 5,000 under absorbed.
Why the others are wrong:
- A: Sign error; difference is under, not over absorption.
- C: Ignores hours adjustment; 15,000 is just budgeted vs. actual overheads without absorption calculation.
- D: Correct direction but wrong amount; variance is 5,000, not 15,000.
Final answer: B
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me