A Level Accounting (9706)•9706/11/O/N/21

Explanation
Overhead absorption variance calculation Steps:
- Calculate predetermined absorption rate: budgeted overheads ÷ budgeted direct labour hours = 48,000 ÷ 12,000 = $4 per hour.
- Calculate absorbed overheads: absorption rate × actual direct labour hours = 76,000.
- Calculate variance: absorbed overheads − actual overheads = 57,000 = $19,000 over absorbed. Why C is correct:
- Over absorption is defined as the excess of absorbed overheads over actual overheads using the predetermined rate formula, resulting in $19,000 here. Why the others are wrong:
- A. 19,000 from the calculation.
- B. Under absorption assumes actual overheads exceed absorbed, but absorbed exceeds actual.
- D. $9,000 under assumes a smaller opposite variance not supported by the figures. Final answer: C
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me