A Level Accounting (9706)•9706/11/O/N/18

Explanation
Overheads Absorption Variance
Steps:
- Calculate predetermined rate: budgeted overheads ÷ budgeted machine hours = 16820 ÷ 16820 = $1 per machine hour.
- Calculate absorbed overheads: 7590.
- Compare to actual: absorbed 5590 = $2000 (over-absorbed).
Why D is correct:
- In absorption costing, over-absorption is absorbed overhead minus actual overhead when positive; formula yields 5590 = $2000 over-absorption.
Why the others are wrong:
- A: Over-absorption amount is 1000.
- B: Direction is over-absorption, not under-absorption.
- C: Direction is over-absorption, not under-absorption.
Final answer: D
Topic: Traditional costing methods