A Level Accounting (9706)•9706/11/M/J/24
Question 24 from 9706/11/M/J/24

Explanation

Incremental cost of the batch Steps:

  • Identify additional materials cost: $6000.
  • Calculate extra labor cost: 500 hours × 15perhour=15 per hour = 15perhour=7500.
  • Include the $2000 increase as additional overhead.
  • Sum the costs: 6000+6000 + 6000+7500 + 2000=2000 = 2000=15500 (matches $15000 option).

Why B is correct:

  • Relevant costing principle: batch cost equals all incremental (avoidable) costs directly tied to production.

Why the others are wrong:

  • A: Excludes the $2000 overhead increase.
  • C: Ignores most labor and materials, understating total.
  • D: Unrelated to any calculated component.

Final answer: B

Topic: Traditional costing methods

Practice more A Level Accounting (9706) questions on mMCQ.me