A Level Accounting (9706)•9706/11/M/J/23

Explanation
Plant-wide overhead absorption rate per direct labour hour
Steps:
- Calculate machining overhead: 48,000
- Calculate assembly overhead: 112,000
- Total overhead: 112,000 = $160,000
- Total direct labour hours: 4000 + 16,000 = 20,000
- Plant-wide rate: 8 per hour
Why C is correct:
- The plant-wide rate uses total budgeted overhead divided by total budgeted direct labour hours, yielding $8 exactly.
Why the others are wrong:
- A: Ignores machining overhead, using only assembly (5.60, close but misapplied).
- B: Averages rates unweighted ((7) ÷ 2 = $9.50, then adjusted wrongly).
- D: Adds insurance to total overhead but divides by assembly hours only (10.30, misbasis).
Final answer: C
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me