A Level Accounting (9706)•9706/11/M/J/22

Explanation
Under-absorption of overheads Steps:
- Calculate predetermined overhead rate: 16 per hour.
- Calculate absorbed overhead: 72,000.
- Under-absorption means actual overhead exceeds absorbed: actual overhead = 12,000 under-absorbed = $84,000. Why D is correct:
- Under-absorption equals actual overhead minus absorbed overhead, so actual = absorbed + under-absorption. Why the others are wrong:
- A: Equals absorbed overhead using budgeted rate on actual hours, ignoring under-absorption.
- B: Possible miscalculation of rate or partial adjustment.
- C: Equals absorbed overhead only, omitting under-absorption addition.
Final answer: D
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me