A Level Accounting (9706)•9706/12/M/J/21

Explanation
Overhead absorption variance using machine hours
Steps:
- Calculate predetermined absorption rate: budgeted overheads ÷ budgeted machine hours = 600,000 ÷ 60,000 = $10 per machine hour.
- Calculate absorbed overheads: 650,000.
- Calculate variance: absorbed overheads - actual overheads = 650,000 - 620,000 = $30,000 over-absorbed.
Why B is correct:
- Over-absorption is defined as absorbed overheads exceeding actual overheads in absorption costing, yielding $30,000 using the formula (rate × actual hours) - actual overheads.
Why the others are wrong:
- A. Assumes under-absorption (actual > absorbed), but absorbed exceeds actual here.
- C. $60,000 understates direction and doubles the variance amount.
- D. 30,000.
Final answer: B
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me