A Level Accounting (9706)•9706/12/M/J/20

Explanation
Job Cost Calculation Using Absorption Costing
Steps:
- Direct labor cost: 6 hours × 120
- Overhead absorption rate: 10 per direct labor hour
- Job overheads: 6 hours × 60
- Total cost: 120 (labor) + 225
Why D is correct:
- Absorption costing requires adding direct materials, direct labor, and overheads absorbed at the predetermined rate based on labor hours, totaling $225.
Why the others are wrong:
- A. $105: Includes only materials and overheads, omitting labor cost.
- B. $165: Includes only materials and labor, omitting overheads.
- C. $180: Likely miscalculates overhead rate or adds incorrect labor hours.
Final answer: D
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me